Report of work planned for the week of Monday: 5/8/2023 to Sunday: 5/14/2023
Project/S.R./Location: The location and description being situated as follows:
SR150/SLD Bellefonte Wall, ECMS 119309
The description and location of the project is as follows: This project is for a wall repair along SR 0150 in Centre County, Bellefonte Borough, Commonwealth of Pennsylvania STATE ROUTE 0150, SECTION SLD at the location as follows:
STATE ROUTE 0150 from Segment 0150 Offset 0856 to Segment 0150 Offset 1267.
Construction includes a new soldier pile retaining wall and rebuilt roadway involving base, binder, and wearing courses, drainage system improvements, pavement markings, and miscellaneous construction as indicated on the approved drawings for a total construction length of approximately 311.00 feet (0.059 miles).
2023
SR150 – Phase 1
- Work: Place E&S control devices, drill caissons and place piles for retaining wall, remove temporary wall fix, cast-in-place retaining wall, backfill, construct new roadway, and place pavement markings.
- Traffic Control SB: Install roadwork signs and barrier, SB traffic will be travelling SB in the NB lane until pattern shift back into SB lane
- Traffic Control NB: Install roadwork and detour signs, close NB lanes and implement the NB
SR150 -Phase 2
- Work: Maintain E&S control devices, drill caissons and place piles for retaining wall, remove temporary wall fix, cast-in-place retaining wall, backfill, construct new roadway, and place pavement markings.
- Traffic Control SB: Maintain roadwork signs, remove barrier, SB traffic will still be travelling SB in the NB lane until pattern shift back into SB lane
- Traffic Control NB: Maintain roadwork and detour signs, NB lanes to remain closed and maintain the NB
SR150 -Phase 3
- Work: Maintain E&S control devices, mill and asphalt overlay of NB lane
- Traffic Control SB: Maintain roadwork signs, traffic travelling SB will stay in SB lane
- Traffic Control NB: Maintain roadwork and detour signs, NB lanes to remain closed and maintain the NB detour